- The Regulation on the Health Principles for Swimming Pools (Resmî Gazete, 6 March 2011, No. 27866) sets the emptying and cleaning duty for pools, including a shorter interval for children's pools. Confirm how it is applied to your facility with your local health directorate and your legal adviser.
- Volume in cubic meters is length × width × average depth, and one cubic meter is 1,000 liters; that single number sets your refill time, your discharge volume and your water cost.
- The Pool Regulation does not specify discharge routes; this is governed by local water authority permits and environmental regulations. Get the route in writing before the first liter leaves the pool.
- An empty pool is a structure under load: groundwater can lift or crack a shell, so the drawdown plan belongs with an engineer, not only with the maintenance calendar.
- The annual clean can be timed to spring start-up, so emptying an outdoor pool in autumn is an operational choice, not a legal duty.
Turkish pool rules require every public pool to be emptied and fully cleaned at least once a year, and children's pools once a month. Hotels usually schedule the annual empty for the quietest week, check the shell and groundwater first, confirm with the local water authority where the water may go, then refill and balance before reopening.
The pool has run since May, the tile at the waterline has gone dull, and the regulation says it must be emptied and fully cleaned at least once a year. The week you choose, and what you check before the first liter leaves the pool, decide whether this is a maintenance job or a repair bill. This guide turns the rule into a plan: the volume arithmetic, the choice of week, a drawdown that protects the shell, the cleaning and inspection list, the refill and the first balance, and the winter question of keeping the pool full or empty.
What does Turkish pool regulation require for emptying and cleaning?
Every pool open to the public must be emptied and fully cleaned at least once a year, and children's pools must be emptied and cleaned once a month. The rule sits in the Regulation on the Health Principles for Swimming Pools, published in the Resmî Gazete on 6 March 2011 (No. 27866) and amended on 15 December 2011 (No. 28143), according to the consolidated text on the Presidency's legislation database. It covers open and closed pools used for swimming, cooling off, fun or sport and open to the public. Health-purpose spa and mineral water pools, and pools not used commercially, are outside it.
The wording is a floor, not a schedule. At least once a year is the minimum the text sets; a pool with heavy bather load may need more, and your provincial health directorate is the body to confirm that with. Children's pools are defined by the same text: at most 50 cm deep, separate from the adult pool, with their own water treatment, emptied and cleaned monthly.
In practice, "emptied and fully cleaned" means the water leaves, the shell is cleaned and inspected, and the pool is refilled. A partial drain and a top-up is not that, and an inspector reading the record book will see the difference. The provincial health directorate inspects the pool, the water and the chemicals every month, including the analysis record books, and the operator keeps laboratory reports for one year to show inspectors. A pool that meets the rules over a calendar year receives a Clean Pool Certificate (Temiz Havuz Sertifikası), which is a reason to keep the annual clean documented rather than remembered.
The annual empty is when you can inspect and repair what water hides: the shell, the joints, the drain covers and the balance tank. The same regulation drives many other duties around water, staff and records, covered in the pool health regulation as a checklist for water, staff and records.
| Duty | Applies to | Frequency | What it means on site |
|---|---|---|---|
| Full empty and clean | Every public pool in scope | At least once a year | Water out, shell cleaned and inspected, refilled |
| Empty and clean | Children's pools (max 50 cm, separate, own treatment) | Monthly | Same procedure on a smaller volume |
| Analysis record book | Every pool | Kept and shown monthly | Laboratory reports retained one year |
| Clean Pool Certificate | Pools meeting the rules over a calendar year | Annual | Awarded for a calendar year that meets the rules |
How do you calculate a hotel pool's volume?
Measure in meters and multiply: length × width × average depth gives cubic meters, and one cubic meter is 1,000 liters. A rectangular pool with one depth is one multiplication. A pool that slopes from shallow to deep uses the average of the two ends: for example, 1.2 m at the steps and 2.0 m at the deep end average 1.6 m.
Split anything that is not a rectangle into rectangles and add them; an L-shape is two boxes, and a circular pool is π × radius² × depth. Subtract what displaces water: wide steps, a beach entry, a raised floor, an integrated spa or a swim-out bench. A 10 percent error on a large pool is a lot of cubic meters.
Check the figure against the as-built drawings and against the water meter on the next fill. If the two disagree, the meter is usually right. The number earns its keep three times: refill time is volume divided by supply rate, the discharge plan needs the volume leaving the site, and the water bill is volume times the local tariff.
Write the figure on the plant room wall and in the pool log so every shift and every contractor uses the same one, and recalculate after any renovation. Dosing depends on the same number, but the doses themselves come from the test kit and the water operator's training, not from a rule of thumb passed between hotels.
TipThe volume formula, worked
For example, a 25 m × 12 m pool with an average depth of 1.5 m holds 450 m³, or 450,000 liters. At a supply of 15 m³ per hour, a full refill takes about 30 hours of continuous filling, before any losses.
Which week should you empty the pool?
The quietest week of the season, in mild weather, with the water supply measured and the staff and contractors booked: not a full week, and not a heatwave. Read your own occupancy curve rather than the calendar. The shoulder weeks either side of the peak usually cost least in turned-away rooms, and the loss is measurable before you commit.
Weather decides the experience. A heatwave turns an empty pool into a complaint, while heavy rain and frost slow the work and the refill. Confirm the water supply first: measure the flow rate and pressure at the hotel's own meter, because a refill that takes days instead of hours changes the whole plan. Check the inspection calendar too. The provincial health directorate inspects monthly, and a pool in the middle of a refill cannot be sampled properly.
Book the people, not just the week: the tiler, the pump technician and the trained pool water operator all need the same dates. Tell guests before they book: put the closure dates in the booking confirmation for those dates, and name the alternative, whether that is a second pool, the sea or a partner property. Do not empty a pool in peak season to fix something cosmetic. A stain or a dull tile line can wait for the planned week; a leaking shell cannot.
ChecklistBefore you commit to a week, work through this list, and keep an eye on daily meter readings a hotel can act on in the weeks around it
- Occupancy forecast below your own threshold
- No heatwave in the forecast
- Mains flow rate and pressure measured at the hotel meter
- Refill duration calculated from volume and flow
- Health directorate inspection date checked
- Tiler, technician and water operator booked
- Guest notice drafted and loaded into the booking confirmation
- Alternative swimming option confirmed
- Discharge route agreed with the local authority
How do you empty a pool without damaging it?
Slowly, with the shell and the groundwater watched, and only after your local water and sewerage authority has told you where the water may go. Groundwater is the first question, not the last. An empty shell weighs far less than the ground pressing on it, and in high groundwater a pool can lift or crack. Ask an engineer, keep a minimum water level if the design calls for it, and find out whether the pool has hydrostatic relief.
Draw the water down in a controlled way: pump or gravity to the balance tank and out, isolate the treatment plant, never run a pump dry, and watch the shell as the level falls. Stop if cracks, movement or unusual seepage appear.
Where the water goes is a local question. No national text was found that states where drained pool water may be discharged, so the answer comes from your water and sewerage authority (İSKİ, ASKİ and their equivalents elsewhere) and your discharge permit. Ask before you start, and keep the answer in writing. Agree the rate as well as the route: a large volume released quickly can surcharge the sewer or flood a neighboring plot, and the authority cares about both. Let the chlorine decay or dechlorinate before discharge as good practice, and follow whatever your authority requires on top of that.
Record the event: start and end meter readings, photographs of the shell at each stage, and the authority's written answer filed with the pool records. Keep the site safe while it is empty: fence the pool, keep depth markings visible, and never let one person work alone in an empty shell.
Watch outAn empty pool is a structure, not a tank
Two checks come before the first liter leaves: an engineer's view on groundwater and shell loading, and a written discharge route from the local water and sewerage authority. Neither can be fixed afterwards.
What should you clean and check while the pool is empty?
Everything you cannot see or reach when it is full: the shell, the waterline, the joints, the inlets, the balance tank and the plant room. Clean the tile line, remove scale, and look for cracks. A structural crack is an engineer's call; a hairline in grout is maintenance. Re-grout, replace loose tiles, check expansion joints, ladder anchors, handrails, depth markings and the pool rules board.
On the hydraulics side, clear skimmers, main drains, equalizer lines and return inlets, and confirm every drain cover is fixed and undamaged, because a missing or loose cover is a serious safety fault. Empty and clean the balance tank, and inspect the float valves and level controls that keep the pool from overflowing or running dry.
In the plant room, check strainer baskets, pump seals, dosing lines and probes, the filter pressure gauge and the backwash sight glass. Probes that read wrong all summer should be calibrated or replaced now. Check the safety equipment too: lifeguard equipment, ring buoys, the rules board and the display board that shows the latest temperature, pH, free chlorine and microbiological results. Photograph each item before it is covered again. Next year's comparison starts from these photographs.
Checklist
- Shell and tile line: scale, cracks, grout, loose tiles
- Fittings: expansion joints, ladder anchors, handrails, depth markings
- Hydraulics: skimmers, main drains, equalizer lines, return inlets, drain covers
- Balance tank: cleaned, float valves, level controls
- Plant room: strainers, pump seals, dosing lines, probes, gauges
- Safety: lifeguard equipment, buoys, rules board, display board
- Records: photographs and notes filed
How do you refill and balance the water before reopening?
Refill at a rate the shell and the supply can take, then balance in order: total alkalinity first, then pH, then disinfectant, then stabilizer, and record the first full set of results. Match the refill rate to the supply and to the engineer's advice. A fast fill on a dry shell stresses finishes, and filling in stages costs nothing but time.
Meter the water. The annual fill is the largest single water event of the year, and the meter reading is both a cost line and a leak check for the weeks that follow. Balance in order, because each step depends on the one before it: total alkalinity gives pH its stability, pH decides how well the disinfectant works, then the disinfectant, then cyanuric acid. The doses come from the test kit and the water operator's training.
Circulate and filter before you test again. A freshly filled pool reads differently from one that has run for a day, and the first reading is not the one to file as normal. Record the first full set: temperature, pH and free chlorine from the operator's tests, plus the daily colour, turbidity and cyanuric acid and the weekly total alkalinity, and post the latest figures where users can see them. The daily routine that follows is covered in measuring and correcting pH and chlorine each day.
Reopening checks: plant running normally, safety equipment in place, signage and fencing correct, and the log signed by the responsible manager. Remember the consequence of a failed sample: a microbiological failure closes the pool until a new sample passes, and a chemical failure brings a written warning first. Finding the problem during the refill is cheaper than finding it in July.
Key pointThe order of first balance
Total alkalinity, then pH, then free chlorine, then cyanuric acid. Each step depends on the one before it, so correcting them in a different order means correcting twice.
Should a seasonal hotel empty the pool for winter or keep it full?
Both work; the choice turns on the shell, the groundwater, the local discharge rules and how the pool will be covered, and the annual clean can be timed to spring start-up either way. Keeping it full keeps the shell loaded, which suits sites with high groundwater. The winter work becomes a cover, reduced circulation, chemistry checks at a lower frequency, and a thorough clean at spring start-up.
Emptying it is only for pools whose shell and groundwater allow it. The pool then needs protection from rain, debris and animals, and the shell needs to be looked at during the winter rather than assumed. The regulation does not force an autumn empty: "at least once a year" can be satisfied at spring start-up, so the winter decision is operational, not legal.
Cover safety matters either way: a cover is a safety device only if it is rated for that use. An unsecured cover on a full pool is a hazard, not a protection. Freeze risk sits mostly in the pipes and the plant, not in the pool: standing water in lines and exposed pipework is the part to drain, following the plant's design. Spring start-up has its own sequence and its own four-week window, and the annual clean slots into it naturally if you did not empty in autumn. The surrounding work is covered in closing a seasonal hotel for winter and reopening a seasonal hotel in the last four weeks.
| Decision | Best when | Winter work | Spring work | Main risk |
|---|---|---|---|---|
| Keep it full | Groundwater is high, or the shell is not designed to stand empty | Cover, reduced circulation, periodic chemistry checks | Full clean and first balance before opening | Unsecured cover, water left unmanaged |
| Empty it | Shell and groundwater allow it, and the local authority approves the discharge | Protect the empty shell from rain and debris, inspect it | Refill and balance from zero | Shell movement or cracking under groundwater pressure |
What to do next
Put the annual empty on next year's calendar now, with four things attached to the date: the pool's volume in cubic meters, the week chosen from your own occupancy curve, the discharge route confirmed in writing by your local water and sewerage authority, and the first balance record filed after reopening. The pieces fit as one loop: the regulation sets the minimum, the volume sets the arithmetic, the week protects the season, the drawdown protects the shell, and the refill and first balance protect the reopening.
Frequently asked questions
Does a hotel pool have to be emptied completely every year?
Yes, for pools in scope of the Regulation on the Health Principles for Swimming Pools (Resmî Gazete, 6 March 2011, No. 27866): each pool is emptied and fully cleaned at least once a year. A partial drain and top-up does not satisfy it. Confirm the scope and the inspection expectations for your own pool with your provincial health directorate.
Where can we discharge drained pool water?
No national text was found that states where drained pool water may be discharged. The rule comes from your local water and sewerage authority and your discharge permit, so ask them before you start and keep the answer in writing. Letting the chlorine decay or dechlorinating first is good practice, and any additional condition comes from the authority.
Do children's pools really need to be emptied every month?
Yes. The regulation defines children's pools as at most 50 cm deep, separate from the adult pool and with their own water treatment, and requires them to be emptied and cleaned monthly. The small volume makes the job quick, and the monthly record is what an inspector will ask for.
Can we do the annual clean at spring opening instead of in autumn?
Yes. The regulation says at least once a year, not once every autumn, so the clean can be timed to spring start-up. The deciding factors are the shell and the groundwater, not the calendar: a pool that must stay full for structural reasons is cleaned in spring, and one that can stand empty may be cleaned in autumn.
How long does emptying and refilling a hotel pool take?
It depends on the volume and on two rates: how fast you can discharge, and how fast the supply refills. Divide the volume by each rate to get hours, then add the cleaning and inspection days. Work it out before you pick the week, because a slow supply can turn a two-day job into a week.